Experience in meeting project goals:
                                   budgeting, cost & quality
Experience on projects with similar requirements
Experience with remodeling projects
References
"Barada-Fuetsch Architects is the best team for your project." We want you to select us because you trust that we have knowledge and experience that we can deliver as the A/E services we have offered. This section offers information on experience and performance - to help build that trust. The results quoted were achieved by John Barada and Ted Fuetsch. 
We have retained the knowledge and the experience we have gained from these projects. We can repeat the performance and improve on the results for you.

Performance in meeting project goals: budgeting, cost control and quality control.  Construction change orders attributed to the A/E team is a common indicator of A/E team performance in preparation of clear and complete construction documents. 

Construction change orders attributed to the owner are often an indicator of A/E team performance in discovering and addressing all of the owner's project requirements. We are proud of our record. The list to the right are the results for the projects completed in the last 5 years where we have been responsible for construction administration and financial performance.


Fallon Paiute Shoshone Health Clinic
, Fallon, NV 10/97 Estimate $1,650,000, Cost $1,400,000 Variation –4%Change Orders; owner 1%, design Team 1%
California Building Remodel Reno, NV 9/98 Estimate $145,000, Cost $142,800, Variation –1% No change orders were issued.
City of Reno 1998 Re-Roofing Reno, NV 9/98 $459,360 budget estimated from 1994 contract. Cost $242,625 Savings 42%, Change Orders; owner 10%, design team 0%
Addition to Lakes Crossing Center, Sparks, NV 10/99 Est. $3,292,000, low bid $3,824,795 Variation 16% Project revised with low bidder to $3,384,795, Variation 2.8% Change Orders: owner 2.2%, design team 1.2%
Pershing County Office Building, Lovelock, NV 7/99 Estimate $606,000, Bid $587,420, Variation –3%.Change Orders; owner 8%, design team 1%
Pyramid Lake Paiute Tribe High School, Nixon NV 9/00 Estimate $7,500,000, Bid 7,193,000, Variation -5%Change Orders: owner 6.4%, design team .5%